How-To Guide

The New NYC Airtightness Requirement, Explained

White wood-framed window
Published
September 18, 2026
Author
Jeremy Riback
Read time
4 min read
Category
How-To Guide
ArchitectsProperty Developers
Article

What the 2025 Energy Code Actually Requires

New York City's 2025 Energy Conservation Code sets a hard air leakage limit for most new commercial and multifamily buildings: 0.40 CFM per square foot of enclosure area, tested at 75 Pascals. That number replaces a patchwork of prescriptive envelope details that architects used to rely on without ever confirming the building actually performed the way the drawings assumed.

The bigger change isn't the number itself. It's how the city verifies it. A single blower-door test at the end of construction can't catch an air leakage problem in time to fix it cheaply, since by then the envelope is closed and finishes are going in. The 2025 code requires staged testing instead: intermediate air leakage tests performed while walls are still open, so gaps in the air barrier get caught while a crew can still access them.

What "Staged Testing While Walls Are Open" Means on Site

In practice, this adds testing checkpoints to the construction schedule that didn't exist before. A typical sequence tests the air barrier at the sheathing stage, again after rough-in penetrations are sealed, and a final test once the building is enclosed. Each stage isolates a different set of failure points: sheathing seams and transitions first, then mechanical, electrical, and plumbing penetrations, then windows, doors, and any remaining assembly gaps.

Why this changes scheduling. A contractor used to a single end-of-job blower-door test now has to hold a testing window open at each stage, which means the trade sequence has to accommodate access for the tester before drywall or exterior cladding closes anything up. Scheduling that late is how projects end up opening finished walls to chase a leak that testing would have caught for a fraction of the cost two months earlier.

Who Has to Coordinate

Three parties own different pieces of this. The architect specifies the air barrier assembly and details the transitions, window-to-wall connections, and penetrations where leaks are most likely to originate. An envelope consultant, brought on early rather than after a failed test, reviews those details against the 0.40 CFM/ft2 target and flags assemblies unlikely to hit it before they're built. The contractor sequences the trades so the air barrier is accessible and testable at each stage, and closes the loop when a test flags a gap.

Where this breaks down. Projects that treat airtightness as a mechanical engineer's problem, or as something to verify after the fact, are the ones that fail a stage test and lose schedule time reopening finished work. Projects that build staged testing into the schedule from the start treat each test as a checkpoint, not a surprise.

Where This Overlaps With Passive House Detailing

Architects who have worked on Passive House projects will recognize this approach. Passive House design has required rigorous air barrier continuity and staged verification for years, well below what the 2025 NYCECC now mandates citywide. The air barrier detailing, continuous insulation, and penetration management that a Passive House envelope requires are the same practices the new code is pushing into mainstream commercial and multifamily construction. Firms with that background aren't learning a new discipline. They're applying a familiar one to a wider set of projects.

That matters for how early a project team should bring in envelope expertise. An architect who has detailed a continuous air barrier before knows where CFM leakage typically originates: sill plates, window rough openings, top-of-wall transitions to roof assemblies, and any penetration added after the air barrier drawings are issued. Catching those in a schedule set, before construction starts, is cheaper than catching them in a stage test.

What to Do Before You Break Ground

If you're an architect or developer on a project subject to the 2025 NYCECC, the airtightness requirement needs to show up in the schedule before it shows up as a testing line item. Build stage test windows into the construction schedule at sheathing, rough-in, and enclosure. Bring an envelope consultant into the design phase, not after a failed test. And make sure the contractor understands that 0.40 CFM/ft2 at 75 Pascals is a target the trades are building toward at every stage, not a single pass-fail moment at the end.

PUR4 Studios designs building envelopes for New York City projects with continuous air barrier detailing informed by Passive House practice, coordinated with staged testing from design through enclosure.